K.D. Stahl Construction Group Inc. Project Update - Bedrosian Tile & Stone Showroom by Kraig Stahl

With the flooring completed and showroom finishes being installed we are getting close to completing this project. The electricians have installed the remaining light fixtures and the HVAC crew is dialing in the last details of their scope. Now that the warehouse space has all the racking in place and the 10,000 lb. crane has been installed, the epoxy finish is being applied to the warehouse space.  We will be updating you as we close in on wrapping up this project and handing it over to Bedrosian Tile & Stone. 

K.D. Stahl Construction Group Inc. San Diego's Leading Commercial General Contractor - Bedrosian Tile & Stone Ground up New Construction

Bedrosian Tile & Stone
Tenant

Gensler
Architect

Dan Dickey
Project Manager

Chris Cherry
Superintendent

Scope of Work:

The new construction project will entail a 30,000 Sq.Ft. tilt-up building, with 6,500 Sq. Ft. of showroom, offices, and site work.

K.D. Stahl Construction Group Inc. San Diego's Leading Commercial General Contractor - Bedrosian Tile & Stone Ground up New Construction
K.D. Stahl Construction Group Inc. - Bedrosian Tile & Stone Ground up New Construction

K.D. Stahl Construction Project Update: Broadway Apartments Standing Walls by Kraig Stahl

 

Location: 
2828 Broadway
San Diego, CA 92102

Broadway Apartments

The CMU wall footings were poured and walls built up to the top of the garage level. Structural pillar footings have been poured and the pillars are being framed in preparation for concrete. 

 
 

The Team

Project Manager
Kraig Stahl

Superintendent
Bill Shepard

 

Architect
Sillman Wright Architects
Brett Tullis AIA LEED AP
7515 Metropolitan Dr. Suite #400
San Diego, CA. 92108
T: 619.294.7515
btullis@sillmanwright.com

Engineering
Naraghi Engineering
Tom Naraghi
16340 Chaparral Way, Bldg. B
Poway, Ca 92064
T: 858.435.4877
tomnaraghi@aol.com

Civil
K & S Engineering, INC.
Hossein Zorromodi
7801 Mission Center Court, Suite 100
San Diego, CA 92108
T: (619) 296-5565
h-zorromodi@ks-engr.com

Electrical
FARD Engineers
Mike Bowden
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
mike@fard.com


Scope:

The 34 Multi-family dwelling consists of 20 one bedroom apartments and 14 studio apartments. This apartment building is 3 story above grade and a basement parking structure.


Plumbing
FARD Engineers
Matt Constant
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
matt@fard.com

Mechanical
FARD Engineers
Bijan Nikravesh
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
bijan@fard.com

Construction management company
Kirt Gilliland
17898 Corazon Place
San Diego, CA 92127
Mobile 619-977-8046 | Office 619-402-1886
e-mail kirt@gillilandcm.com

K.D. Stahl Construction Group Inc. Project Update - Bedrosian Tile & Stone Showroom by Kraig Stahl

With just a few more tiles to go, the flooring of the Bedrosian Showroom is almost complete. Electricians have installed the majority of the light fixtures with just a few left to complete their scope. The warehouse space has all the racking in place and the 10,000 lb. crane has been installed. We will be updating you as we close in on wrapping up this project and handing it over to Bedrosian Tile & Stone. 

K.D. Stahl Construction Group Inc. San Diego's Leading Commercial General Contractor - Bedrosian Tile & Stone Ground up New Construction

Bedrosian Tile & Stone
Tenant

Gensler
Architect

Dan Dickey
Project Manager

Chris Cherry
Superintendent

Scope of Work:

The new construction project will entail a 30,000 Sq.Ft. tilt-up building, with 6,500 Sq. Ft. of showroom, offices, and site work.

K.D. Stahl Construction Group Inc. San Diego's Leading Commercial General Contractor - Bedrosian Tile & Stone Ground up New Construction
K.D. Stahl Construction Group Inc. - Bedrosian Tile & Stone Ground up New Construction
K.D. Stahl Construction Group Inc. - Bedrosian Tile & Stone Ground up New Construction
K.D. Stahl Construction Group Inc. San Diego's Leading Commercial General Contractor - Bedrosian Tile & Stone Ground up New Construction

K.D. Stahl Construction Group Inc - Saint Therese Parish Restoration Construction Project by Sean Stahl

The Saint Therese Parish Restoration is complete. See scope below for more information on the restorations made for this Cathedral.

Location:

6016 Camino Rico
San Diego, Ca 92120

K.D. Stahl Construction Group Inc. - Saint Therese Parish Restoration Construction Project

Scope of Work:


Scope A. Renovate existing bell tower built in 1957 by removing the existing exterior plaster skin and ornamentation. Repair damaged framing and waterproof the structure with a self-sealing type waterproof membrane prior to applying the new lath and plaster system . All ornamentation will be replicated in foam. Tile dome will be rehabilitated in place.

The existing church tiled roof will be removed so the substrate can be repaired and receive a new self-sealing waterproof membrane prior to reinstalling the existing roof tiles. The interior TPO roofs inside the tower will be replaced as well. All existing gutters and downspouts will be replicated and replaced to match existing.

Scope B. The existing arcades between the church and the office have sustained flood damage thru the years, to remedy this the existing storm drain system will be rebuilt and adjacent grades adjusted to keep storm water from entering the arcade . The existing Spanish tile flooring will be salvaged. Columns will be stripped and repaired where water damage has occurred. The existing concrete substrate will be removed to allow for the new storm drains and replaced with Paver stones. The salvaged Spanish tiles will be applied as decorative base to the existing columns in the arcade.

K.D. Stahl Construction Group Inc. - Saint Therese Parish Restoration Construction Project

We had to remove the original bell tower due to the structure failing. We reframed the structural support for the dome and restored the tile and cross to its original design from 1957. 

 
We removed the tower to rebuild its failing structure and retile the dome before setting it back on. #kdstahlprojectupdate
st.theresa_towerremoval-2.jpg
st.theresa_towerremoval-3.jpg

K.D. Stahl Construction Project Update: cCare Nordahl Medical Centre Tenant Improvement by Sean Stahl

cCare has added new square footage to there centre and has added a new CT & PET scanning machine. Getting this equipment in the building had to be creatively thought out and planned. See the photos below to see what we had to do.  

Location:

838 Nordahl Road, Suite 300
San Marcos, Ca 92069

K.D. Stahl Construction Finalized Medical Office Tenant Improvement by Kraig Stahl

K.D. Stahl Construction Group Inc. - Medical Tenant Improvement
 
 

Project Update:

We've completed the medical office tenant improvement in Encinitas, California for a a new children's primary care physician group. 

 

Located at:
 499 El Camino Real Ste. 100
Encinitas, Ca 92024

 
 

Scope of Work: 

Complete interior demolition of an existing 8,071 SF one story medical office and new tenant improvements for medical office practice that specializes in children’s primary care.


Team:

Architect
Reilly and Associates

 
K.D. Stahl Construction Group Inc. - Tenant Improvement and Exterior Renovation In San Diego County.
K.D. Stahl Construction Group Inc. - Medical Tenant Improvement
K.D. Stahl Construction Group Inc. - Tenant Improvement and Exterior Renovation In San Diego County.

K.D. Stahl Construction Closing in on the Finishes at Scripps Summit Pointe by Sean Stahl

summit-point-5.jpg
 
 

Project Update:

The exterior hardscape and landscape is complete. We are now wrapping up some interior details and will be handing over the building to the owners soon. 

 

Located at:
10641 Scripps Summit Court
San Diego, California
 

 
 

Scope of Work: 

The building's exteriors will be built out with new finishes and features as well as various amount of hardscape improvements totaling 4,764 sqft. Addition of a BBQ Bar and Trellis to the exterior. Modifications to existing exterior canopy & exterior stairwell facades. Modifications to existing exterior storefront door openings. The interior renovations include a built to suite renovation. 


Team:

Architect
MAA Architects, Inc.

Interior Design
DesignCorp

Structural
Miyamoto International, Inc.

Mechanical & Plumbing
Harinton Mechanical Design

Electrical
Nutter Electrical

 
K.D. Stahl Construction Group Inc. - Tenant Improvement and Exterior Renovation In San Diego County.
K.D. Stahl Construction Group Inc. - Tenant Improvement and Exterior Renovation In San Diego County.
K.D. Stahl Construction Group Inc. - Tenant Improvement and Exterior Renovation In San Diego County.

K.D. Stahl Construction Project Update: Broadway Apartments Begins Fine Grade by Kraig Stahl

 

Location: 
2828 Broadway
San Diego, CA 92102

Broadway Apartments 

With just a days worth of soil to be removed we are looking at a total of 14,000 yards removed in total. Next week we will begin excavation for footings and underground utilities. 

 
 

The Team

Project Manager
Bob Turner

Superintendent
Bill Shepard

 

Architect
Sillman Wright Architects
Brett Tullis AIA LEED AP
7515 Metropolitan Dr. Suite #400
San Diego, CA. 92108
T: 619.294.7515
btullis@sillmanwright.com

Engineering
Naraghi Engineering
Tom Naraghi
16340 Chaparral Way, Bldg. B
Poway, Ca 92064
T: 858.435.4877
tomnaraghi@aol.com

Civil
K & S Engineering, INC.
Hossein Zorromodi
7801 Mission Center Court, Suite 100
San Diego, CA 92108
T: (619) 296-5565
h-zorromodi@ks-engr.com

Electrical
FARD Engineers
Mike Bowden
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
mike@fard.com


Scope:

The 34 Multi-family dwelling consists of 20 one bedroom apartments and 14 studio apartments. This apartment building is 3 story above grade and a basement parking structure.


Plumbing
FARD Engineers
Matt Constant
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
matt@fard.com

Mechanical
FARD Engineers
Bijan Nikravesh
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
bijan@fard.com

Construction management company
Kirt Gilliland
17898 Corazon Place
San Diego, CA 92127
Mobile 619-977-8046 | Office 619-402-1886
e-mail kirt@gillilandcm.com

K.D. Stahl Construction Project Update: Broadway Apartments Breaking Ground by Kraig Stahl

K.D. Stahl Construction Group Inc. - Broadway Apartments Construction in San Diego California 
 

Location: 
2828 Broadway
San Diego, CA 92102

Broadway Apartments 

The excavating is in progress as we remove the excess soil for the foundation and underground parking structure for the future home of the Broadway Apartments just east of our Downtown San Diego Landscape. 

 
 

The Team

Project Manager
Bob Turner

Superintendent
Bill Shepard

 

Architect
Sillman Wright Architects
Brett Tullis AIA LEED AP
7515 Metropolitan Dr. Suite #400
San Diego, CA. 92108
T: 619.294.7515
btullis@sillmanwright.com

Engineering
Naraghi Engineering
Tom Naraghi
16340 Chaparral Way, Bldg. B
Poway, Ca 92064
T: 858.435.4877
tomnaraghi@aol.com

Civil
K & S Engineering, INC.
Hossein Zorromodi
7801 Mission Center Court, Suite 100
San Diego, CA 92108
T: (619) 296-5565
h-zorromodi@ks-engr.com

Electrical
FARD Engineers
Mike Bowden
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
mike@fard.com


Scope:

The 34 Multi-family dwellings consist of 20 One bedroom Apartments and 14 Studio Apartments. This apartment building is 3 story above grade and a basement parking structure.


Plumbing
FARD Engineers
Matt Constant
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
matt@fard.com

Mechanical
FARD Engineers
Bijan Nikravesh
3550 Camino del Rio North, Suite 204
San Diego, CA 92108
T: (619) 235-0022
bijan@fard.com

Construction management company
Kirt Gilliland
17898 Corazon Place
San Diego, CA 92127
Mobile 619-977-8046 | Office 619-402-1886
e-mail kirt@gillilandcm.com